Construction workers busy at wind farm
August 3, 2010

Pouring foundations at Laredo Ridge Wind Farm.
As of Monday, Aug. 2, three foundations were complete, and two had the base portion of the foundations in place. This week, Edison Mission Energy said there are about 40 construction personnel working on site, along with about 10 management personnel. A total of 23 foundations have been excavated, and eight more foundations are ready for placement of concrete. About 15 percent of the access roads have been finished.
The wind farm, located northeast of Petersburg, will include 54 towers when completed.